West Lake Bridge
October 17, 2024 - All Contractor Project Constructon has been completed.
In an effort to lower project costs, the Eagle County Road and Bridge Department will be responsible for the re-vegetation of the site as well as pavement markings.
Pavement markings will be highly dependent upon the weather.
Utility relocations of CenturyLink and Comcast facilities back onto the new bridge still need to be completed by those utility providers. If you experience any issues with those utilities, the following are my contacts for Comcast and CenturyLink.
Centurylink Contact: Jason Sharpe
Phone: 970.328.8290
Email: Jason.Sharpe@Lumen.com
Comcast Contact: Brett Westphall
Phone: 720.979.1921
Email: brett_westphall@comcast.com
This project was completed nearly a month ahead for the project completion date of Friday, November 15, 2024.
I, along with the contractor, Gould Construction, would like to express my thanks and gratitude to the residents in the area for your patience, cooperation and understanding throughout the construction process. Your reward is this fabulous bridge.
Any questions or comments pertaining to the project should be directed to Eagle County Senior Staff Engineer Rickie Davies at 970-328-3567 or richard.davies@eaglecounty.us.
October 7, 2024 - All project road closures have been completed.
July 22, 2024 - The Eagle County Engineering and Road & Bridge Departments will replace the existing West Lake Creek Road bridge over East Lake Creek. The project will be constructed under traffic. Automated flagger assistance devices will be in place to control traffic flow, with traffic often reduced to one lane. Due to the site's constraints, four road closures will be required to construct the bridge. A closure will be required for the placement of the bridge abutments, and an additional closure approximately a week later for the placement of the bridge decks. These closures will need to be implemented for each half of the bridge, first, the north half will be constructed, and then the south half.
Construction is scheduled to start on Monday, August 5, 2024, with a completion date of Friday, November 15, 2024.
Additional press releases will be posted prior to the actual closures of the road.
The tentative dates of the closures are:
· Thursday, August 22, 2024
· Thursday, August 29, 2024
· Tuesday, September 24, 2024
· Monday, September 30, 2024
Each road closure is tentatively scheduled for 10:00 am to 2:00 pm.
The tentative Thursday, August 22, 2024, and Thursday, August 29, 2024 road closures will also require the de-energization of the overhead power lines due to the proximity of construction equipment to those overhead power lines during the duration of the closure.
“The West Lake Creek Road Bridge was originally constructed in 1940. Due to the structure’s age and condition, it has been determined that replacement of the structure is necessary to protect the public health, safety, and welfare of the residents of Eagle County,” said Eagle County Senior Staff Engineer Rickie Davies.
The Eagle County Engineering Department directed the replacement of this bridge, which the contractor, Gould Construction, LLC, will perform
Any questions or comments about the project should be directed to Eagle County Senior Staff Engineer Rickie Davies at 970-328-3567 or richard.davies@eaglecounty.us.